Seoul-Pusan High Speed Line, Seoul Korea

International

Works completed

Seoul, Korea

Category

Railway Works – Subways

Work start

1997

End of worls

2002

Construction of 3 viaducts with box decks entirely prefabricated in reinforced concrete according to the “Ferrocemento” system, for a total of 214 spans of 25 m, and a total length of 5,350 m. The decks, weighing 6,000 KN each, are installed by simply supporting them and subsequently made continuous with casting on-site and pre-stressing cables.